Skip to content

Diary

12/01/2026

  • Visited We Do Bamboo to assess locally available bamboo species and their dimensional manufacturing capabilities relevant to engineering and testing applications.

13/01/2026

  • Fabricademy global session

14/01/2026

  • Fabricademy local session
  • We Do Bamboo report discussion with Katoh-San

15/01/2026

  • 2nd Visit - We Do Bamboo
    • A follow up meeeting to better understand;
      • Their drying process
      • Sugar removal protocols
    • Request We Do Bamboo for samples to be later used in materials testing
    • Visit Report 2nd Visit - Report
  • Update Gantt Chart

16/01/2026

  • Received and reviewed report on We-Do-Bamboo bamboo treatment procedure
    • Report Summary
  • Started research on Young's Modulus rig requirements

17/01/2026

  • Completed research on Young's Modulus rig requirements here
  • Started initial sketches

18/01/2026

  • Start initial Young's Modulus rig sketch

21/01/2026

  • [] Completed initial sketch of Young's Modulus rig

24/01/2026

  • Meeting with Katoh-San:
    • Discussed Young's Modulus testing rig design
    • Added some specifications to be taken into consideration during design
    • Finalized on the force application mechanism (rotating motor with wheel to pull on a wire)
    • Prioritize making design changes on FKS Main Frame as suggested by Anastasia

26/01/2026

  • [] Update work schedule
  • Start on seat modifications

27/01/2026

  • [] Finalize seat modifications